SPOKANE, WA - April 29, 2009 - Minera Andes Inc. (TSX: MAI and US OTC: MNEAF)
is pleased to announce details of the San José mine production for the
first quarter of 2009. The San José project is owned by Minera Santa
Cruz S.A. ("MSC"), which in turn is owned 49% by Minera Andes and 51%
by Hochschild Mining plc ("Hochschild") (HOCM.L: Reuters and HOC LN:
Bloomberg - London Stock Exchange). Hochschild is the operator of San
José. Production for San José in the first quarter (on a co-product
basis) totaled 1,299,000 ounces of silver at a cash cost of $4.99 per
ounce and 16,560 ounces of gold at a cash operating cost of $357 per
ounce, of which 49% of the production is attributable to Minera Andes.
(All dollars in this news release are US dollars.)
The San José gold/silver mine saw a decrease in gold and silver
production and a significant lowering of unit operating costs in Q1 2009
compared to Q4 2008 as reported by MSC to the owners. Silver
production was 2% lower and gold production was 5% lower in Q1 2009
compared to the previous quarter, because approximately 20% of the
mill feed was derived from low-grade surface stockpiles. This was
partially offset by the higher tonnage being treated in the current
quarter. Unit operating costs were lower due to increased production
and the economies of scale associated with the processing capacity
expansion completed in Q4 of 2008.
Production cash operating costs were $12.2 million. Total
operating cash costs during Q1 2009 decreased approximately 28%
compared to Q4 2008 mainly due to lower costs for marketing, labor,
supplies, energy, and repairs and maintenance, all of which was
partially offset by an increase in the tonnage mined and processed.
The cash cost per tonne was $111.80 in Q1 2009. The cash cost per
tonne decreased approximately 34% in Q1 2009 compared to Q4 2008 due
to the lower total cash costs explained above and, to a lesser extent,
by the higher volume extracted from the mine and processed at the
plant.
Cash cost per ounce of silver and gold, on a co-product basis,
decreased approximately 28% and 21% respectively in the Q1 2009
compared to Q4 2008.
Mill throughput increased 10% in Q1 2009 compared to the previous
quarter due to the plant expansion completed in October, which was
partially offset by the lower number of production days in Q1 2009 (87
days) than in Q4 2008 (95 days). The San José mine entered into full
commercial production on January 1, 2008, however there were 317,000
ounces of silver and 4,319 ounces of gold produced in the second half of
2007 during the commissioning period. A planned expansion project to
double the original design capacity of the processing plant from 750
tonnes per day ("MTPD") to 1,500 MTPD was completed in October 2008.
Mill production has now been ramped up to the expanded capacity,
and the first quarter of 2009 marked the first full quarter of
production at near the expanded capacity rate. Approximately half of
the concentrate produced by the mill is converted on site to doré
bullion.
MSC sales of precious metal were lower in Q1 2009 compared to Q4
2008 because of current negotiations for new contracts and better
conditions for the sale of doré bars and concentrates. As a result,
the company had accumulated final product inventory of silver and gold
that have been sold in Q2 2009. Product inventories at the end of Q1
2009 consisted of 7,437 kg of high-grade precipitate from the Gekko
electrowinning circuit (3,951 kilograms at the end of Q4 2008), 12,110
kilograms of silver-gold doré bullion (9,954 kilograms at the end of
Q4 2008), and 1,449 tonnes of silver-gold concentrate (195 tonnes at
the end of Q4 2008), containing 11,290 ounces of gold and 898,000
ounces of silver (6,190 ounces of gold and 459,000 ounces of silver at
the end of Q4 2008).
SAN JOSÉ MINE PRODUCTION *
Production
|
Q1
2009 |
Q4
2008 |
Q1
2008 |
Ore production (tonnes) |
118,986 |
107,875 |
59,897 |
Average head grade silver (g/t) |
427 |
463 |
624 |
Average head grade gold (g/t) |
5.29 |
5.91 |
7.10 |
Silver produced (ounces) |
1,299,000 |
1,329,000 |
968,000 |
Gold produced (ounces) |
16,560 |
17,370 |
12,140 |
Net silver sold (ounces) |
838,000 |
1,135,000 |
323,000 |
Net gold sold (ounces) |
11,380 |
13,930 |
5,050 |
*The company has a 49% interest in MSC that owns the San José mine.
SAN JOSÉ MINE COSTS
Costs
|
Q1
2009 |
Q4
2008 |
Q1
2008 |
Operating Cash Costs ($) |
12,219,000 |
16,987,000 |
8,719,000 |
Operating cash cost/tonne** ($/t) |
111.8 |
168.2 |
141.6 |
Operating cash cost/oz Au ($/oz) |
357 |
494 |
286 |
Operating cash cost/oz Ag ($/oz) |
4.99 |
6.32 |
5.42 |
** The cash cost per tonne considers both the extracted and processed tonnes.
Work is underway to also increase mine production from 750 MTPD to
1,500 MTPD, primarily by accessing the Kospi vein, located between
the Huevos Verdes and Frea veins which are the source of the current
production. Production from the Kospi vein is anticipated to commence
during the second quarter of 2009. In the meantime, mill feed is
being generated from expanded mine production at the Huevos Verde and
Frea veins and from a surface stockpile of low-grade ore.
Allen V. Ambrose, Minera Andes' President, who is a "qualified
person" as defined by National Instrument 43-101, is responsible for
the information used in this news release and has supervised the
preparation of the information and reviewed all information used in
this news release.
Minera Andes is a gold, silver and copper exploration company
working in Argentina. The Corporation holds or has an interest in
approximately 304,000 acres of mineral exploration land in Argentina,
including the properties comprising the 49% owned San José silver/gold
mine. Minera Andes is also exploring the Los Azules copper project
in San Juan province, where a scoping study has been completed and a
43-101 technical report filed. Other exploration properties,
primarily silver and gold, are being evaluated in southern Argentina.
The Corporation presently has 230,538,851 shares issued and
outstanding.
This news is submitted by Allen V. Ambrose, CEO, President and Director of Minera Andes Inc.
For further information, please contact: Art Johnson at the
Spokane office, or Krister A. Kottmeier, investor relations -- Canada,
at the Vancouver office. Visit our Web site: www.minandes.com.
Spokane Office
111 East Magnesium Road; Ste. A
Spokane, WA 99208 USA
Phone: (509) 921-7322
E-mail:
info@minandes.com |
Vancouver Office
911-470 Granville Street
Vancouver, B.C. V6C 1V5
Phone: (604) 689-7017; 877-689-7018
E-mail:
ircanada@minandes.com |
Non-GAAP Financial Measures:
In this news release, we use the term "operating cash cost."
Operating cash costs are defined as the sum of the geology, mining,
processing plant, general and administration costs as well as
royalties, refining and treatment charges and sales costs applied to
doré, but with respect to concentrate sales do not include refining,
treatment charges and sales costs. The operating cash costs per ounce
are calculated on a co-product basis by dividing the respective
proportionate share of the total costs for the period for each metal
by the ounces of each respective metal produced. The proportionate
share of the total costs is calculated by multiplying the total cash
costs by the percentage of total production value that the respective
metal represents. For 2008, approximately 58% of the value of the
production was derived from silver and 42% was derived from gold based
on the year 2008 average London PM fix for silver and for gold. We
use operating cash cost per ounce as an operating indicator. We
provide this measure to our investors to allow them to also monitor
operational efficiency of MSC's mine at San José. Operating cash cost
per ounce should be considered as non-GAAP Financial Measure and
should not be considered in isolation or as a substitute for measures
of performance prepared in accordance with GAAP. There are material
limitations associated with the use of such non-GAAP Financial
Measures. Since these measures do not incorporate revenues, changes in
working capital and non-operating cash costs, they are not necessarily
indicative of operating profit or cash flow from operations as
determined under GAAP. Changes in numerous factors include, but are not
limited to, mining rates, milling rates, silver and gold grades,
silver and gold recoveries, and the costs of labor, consumables and
mine site operations general and administrative activities that can
cause these measures to increase or decrease.
Caution Concerning Forward-Looking Statements:
This news release contains forward-looking statements and
forward-looking information within the meaning of applicable US and
Canadian securities laws. Such forward-looking statements or information
include expected production at MSC's San José Project. In making the
forward-looking statements and providing the forward-looking
information, we have made numerous assumptions. Although our management
believes that the assumptions made and the expectations represented by
such statements or information are reasonable, there can be no
assurance that the forward-looking statements will prove to be
accurate. Forward-looking statements and information involve known and
unknown risks, uncertainties and other factors that may cause our
actual results to be materially different from that expressed or
implied by such forward-looking information. Such risks, uncertainties
and other factors include among other things, declines in the price
of gold, silver, copper and other base metals, capital and operating
cost increases, changes in general economic and business conditions,
including changes in interest rates and the demand for base metals,
economic and political instability in Argentina, discrepancies between
actual and estimated production and mineral reserves and resource,
operational and development risk, and the speculative nature of
mineral exploration and regulatory risks.
Readers should not place undue reliance on forward-looking
statements or information. We undertake no obligation to reissue or
update forward-looking statements or information as a result of new
information or events after the date hereof except as may be required
by law. See our annual information form for additional information on
risks, uncertainties and other factors relating to the forward-looking
statements and information. All forward-looking statements and
information made in this news release are qualified by this cautionary
statement. Minera Andes' joint venture partner, a subsidiary of
Hochschild Mining plc, and its affiliates do not accept responsibility
for the use of project data or the adequacy or accuracy of this
release.