SPOKANE,
WA----February 05, 2009---- Minera Andes Inc. (TSX: MAI and US OTC:
MNEAF) is pleased to announce the results of a preliminary assessment
("PA") on the Los Azules Copper Project (the "Project") located in the
San Juan Province of western central Argentina. The deposit as
currently defined is open in several directions, and further drilling
will be required to fully define the limits of the mineralization,
especially along the strike to the north and at depth.
The Project is an exploration area comprised of adjoining
properties that straddle a large copper porphyry system and is subject
to an Option Agreement. The properties are owned by Minera Andes
through its subsidiary company, Minera Andes S.A. (the "MASA
Properties" and "MASA", respectively) and by Xstrata Copper, one of
the commodity business units within Xstrata plc (London Stock
Exchange: XTA.L and Zurich Stock Exchange: XTRZn.S), through Xstrata
Queensland Limited and its subsidiary company, MIM Argentina
Exploraciones S.A. (the "MIM Properties" and "MIM", respectively).
Highlights
Highlights of the study are as follows (all figures are expressed in US dollars unless otherwise stated):
- The base case for the Project on a pre-tax basis indicates a
Net Present Value ("NPV") of $496 million and an Internal Rate of
Return ("IRR") of 10.8% (using $1.90/lb copper, 8% discount rate,
$70/tonne treatment charge and $0.075/lb refining charge).
- Capital payback in 6.4 years.
- Average copper-in-concentrate production estimated at
170,000 tonnes per annum for 23.6 years. Annual by-product production
estimated to average 38,000 ounces of gold, and 1.26 million ounces of
silver.
- C-1 Life of Mine ("LOM") cash costs (net of by-product credits) are estimated to average $0.85 per pound of copper mined.
- The Project would generate approximately 550 permanent jobs.
The salient details of the PA are summarized in the table below
(all dollar figures are in US dollars unless otherwise stated):
NPV ($1.90/lb Cu, 8% discount rate) |
$496 million |
IRR |
10.8% |
Initial Capital Expenditure |
$2,747 million |
LOM Average Operating Costs |
$7.59/t ore |
LOM C-1 Cash Costs (net by-product credits) |
$0.85/lb Cu mined |
Nominal Mill Capacity |
100,000 tpd |
Annual Throughput |
36 million tonnes |
Mine Life |
23.6 years |
Life-of-Mine Strip Ratio |
1.50 |
LOM average annual copper-in-concentrate production |
170,000 tonnes |
First 5 Years average annual copper-in-concentrate production |
213,000 tonnes |
The PA is preliminary in nature and includes the use of
inferred resources which are considered too speculative geologically
to have the economic considerations applied to them that would enable
them to be categorized as mineral reserves. Thus, there is no
certainty that the results of the PA will be realized. Actual results
may vary, perhaps materially.
The PA was finalized by Samuel Engineering, Inc. and Randolph P.
Schneider, MAusIMM. The PA was managed by MTB Project Management
Professionals (project management, infrastructure, capital and operating
costs) and Robert Sim (SIM Geological Inc.) and Bruce Davis (BD
Resource Consulting Inc.) developed the resource estimate, Ken Rippere
completed pit slope studies, while Bill Rose (WLR Consulting Inc.)
developed the mine plan and production schedule, C.H. Plenge & Cia
(metallurgy), Samuel Engineering (process engineering, infrastructure,
capital and operating costs, cash flow modeling, and valuation),
Vector Engineering (tailings, waste rock, environmental management,
capital and operating costs, and baseline environmental and
socioeconomic studies).
Project Economics
The PA contains a cash flow valuation model based upon the
geological and engineering work completed to date and technical and
cost inputs developed by Samuel Engineering and MTB. The base case was
developed using long term forecast metal prices of $1.90/lb for
copper, $750/oz for gold, and $12/oz for silver.
The following table shows the NPV of the base case at various discount rates:
Discount Rate (Real) |
NPV |
0% |
$4,691 million |
5% |
$1,399 million |
8% |
$496 million |
10% |
$113 million |
15% |
$(428) million |
The following chart shows the sensitivity of the base case's NPV
and IRR to changes in the copper price: (8% real discount rate):

Resources
The resource block model used in the PA were reported in the technical
report titled "Los Azules Copper Project San Juan Province, Argentina"
dated September 26, 2008 and filed under the Company's profile at www.sedar.com
in October 2008 (the "October Technical Report"). That resource
estimate determined Inferred Mineral Resources of 922 million tonnes
grading 0.55% copper at a 0.35% total copper cutoff. Mineral resources
that are not mineral reserves do not have demonstrated economic
viability.
The resource block model was used to evaluate potential economic pit
limits using the floating cone algorithm and develop a mine plan and
production schedule for the PA. The resulting designed ultimate pit was
estimated to contain 843 million tonnes of Inferred Mineral Resources
grading 0.51% copper above an internal cutoff of 0.22% copper. A
total of 1,273 million tonnes of waste rock were also estimated within
this pit. A mine production schedule from these estimates indicates
150 million tonnes of pre-production stripping and a mine life of 23.6
years. The average stripping ratio over the life of the mine is
projected at about 1.5:1 (tonnes of waste per tonne of ore).
The PA is preliminary in nature and includes the use of inferred
resources which are considered too speculative geologically to have
the economic considerations applied to them that would enable them to
be categorized as mineral reserves. Thus, there is no certainty that
the results of the PA will be realized. Actual results may vary,
perhaps materially.
Mining & Milling
The Project will utilize conventional mining and milling processes and will benefit from having a higher grade copper core.
Production is scheduled to deliver 100,000 tonnes per day (36 million
tonnes per year) of sulphide ore to the primary crusher for 23.6 years.
The milling and concentrator plant are forecast to produce, on
average, 170,000 tonnes per year of copper in concentrate, 38,000
ounces per year of gold, and 1.26 million ounces per year of silver.
Average LOM metallurgical recoveries have been estimated to be 92.5%
for copper, 61% for gold, and 66% for silver, producing a copper
concentrate grading on average 31.9% copper, 2.2 g/t gold and 74 g/t
silver.
Capital Costs
The following table summarizes the capital cost estimates for the Project:
Direct Capital Costs |
$1,118 million |
Indirect Capital Costs |
$486 million |
Owner Direct and Indirect Capital Costs |
$602 million |
Additional Costs |
$541 million |
Total (Base Case) |
$2,747 million |
Upfront Working Capital |
$39 million |
LOM Sustaining Capital Costs |
$704 million |
The capital cost estimates have been compiled with an accuracy level of --35% to +35%.
Operating Costs
The average LOM operating cost is estimated to be $7.59 per tonne of ore
and the C-1 cash costs (net of by-products) over the LOM will average
$0.85 per pound of copper mined. C-1 cash costs include at-mine cash
operating costs, concentrate transportation and freight costs and all
treatment and refining charges.
Infrastructure
The Project is in a remote location near the border of Chile in an
isolated section of the Argentinean Andes at an elevation ranging from
3,500 to 4,500 meters above sea level (masl). Consequently, no
infrastructure is present. In addition, there are no nearby towns and/or
settlements. The key access issue for the Project throughout the year
is road closures due to snow and high stream flows in the spring. The
snowline is at an approximate elevation of 3,000 masl. Presently, the
Project is accessible approximately 5 months out of the year with
snow removal along the existing central road and after the snow fall
season.
San Juan is a major regional center serviced by an airport and highways.
An existing highway extends from San Juan to a wide valley in which
the community of Calingasta is located. Three potential mine access
roads have been considered: a northern route, a central (existing)
route, and a southern route. Both the central and southern routes were
discarded due to their capital and operating costs as the length,
terrain and high altitude crossings would likely make the routes prone
to significant snowfalls and require snow removal operations.
Therefore, the northern route was selected for the economic valuation
of the Project.
Given the remote location of the Project a man camp facility will be
provided onsite. It is assumed to contain facilities for 500-600
individuals at any given time. The man camp will also contain dining and
recreation facilities.
The Calingasta substation is the nearest source of power to the Project;
however, it is isolated from the provincial network. Power supply to
the region is currently satisfied by means of local hydro or thermal
generation.
The infrastructure facilities addressed by the capital cost estimate
include on-site ancillary facilities and infrastructure (man camp,
offices, and other buildings), off-site infrastructure (access roads,
power lines, concentrate and fresh water pipelines) and tailings
impoundment.
Environmental
Preliminary baseline studies completed to date have included initial
hydrologic studies of surface water quality, climate, and biological
studies of the local flora and fauna.
Property Agreements
The Project is subject to an Option Agreement dated November 2, 2007.
Under the Option Agreement, MASA has the right to earn a 100% interest
in the MIM Properties by spending at least US$1.0 million on the MIM
Properties by November 2010, maintaining the property in good standing
and delivering to Xstrata Copper an independent scoping study that
contains an economic evaluation of inferred mineral resources and a
technical report prepared in accordance with National Instrument 43-101
"Standards of Disclosure for Mineral Properties" ("NI 43-101") in
respect of the combined MIM Properties and MASA Properties (the
"Combined Property") and delivering a notice of exercise. If in the
opinion of Xstrata Copper, the independent scoping study and technical
report shows the potential to economically produce 100,000 tonnes (224
million pounds) of contained copper per year for 10 years or more on
the Combined Properties then MIM will have a right to earn a 51%
interest in the Combined Property (the "Back-in Right"). To satisfy
the conditions of the Back-in Right, Xstrata Copper must assume
control and responsibility for the Combined Property, make a cash
payment to Minera Andes of three times MASA's and it affiliates'
direct expenditures incurred and paid on the Combined Properties after
the 25th of November 2005 and complete a bankable feasibility study
within five years of its election to exercise the Back-in Right. In
the event that the independent scoping study and technical report do
not, in Xstrata Copper's opinion, meet the criterion contemplated
above, Xstrata Copper's interest would be limited to a right of first
refusal on a sale of the Combined Property, or any part thereof or
interest therein.
Certain of the MIM Properties are subject to an underlying option
agreement, which is the subject of a dispute between Xstrata Copper, as
option holder, and Solitario Argentina S.A. ("Solitario"), as the
grantor of that option and the holder of a back-in right of up to 25%,
exercisable upon the satisfaction of certain conditions, within 36
months after the exercise of the option by Xstrata Copper. The dispute
surrounds the validity of the 36 month restriction described above.
If Solitario is successful, MIM's interest in substantially all of the
MIM Properties may be reduced by up to 25% and upon exercise of the
MASA Option, MASA's interest in that part of the Combined Property may
be similarly reduced (the "Solitario Claim").
A technical report in support of the PA, prepared in accordance with NI
43-101 will be filed on SEDAR (www.sedar.com) within 45 days. This
news release was prepared by, or under the supervision of, Mr. Allen
Ambrose, President of Minera Andes, a "qualified person" within the
meaning of NI 43-101. For (i) the effective date of the resource
estimate contained herein; (ii) a description of the key assumptions,
parameters and methods used to estimate the mineral resources referred
to in this news release; and (iii) a general discussion of the extent
to which the estimate of mineral resources may be materially affected
by any unknown environmental, permitting, legal, title, taxation,
socio-political, marketing, or other relevant issues, please refer to
the October Technical Report.
Minera Andes is a gold, silver and copper exploration company working in
Argentina. The Company holds about 304,000 acres of mineral
exploration land in Argentina. The producing San José silver/gold mine
is 49% owned by Minera Andes through a joint venture. Minera Andes is
also exploring the Los Azules copper project in San Juan province,
where an exploration program has defined a resource and a scoping
study has been completed. Other exploration properties, primarily
silver and gold, are being evaluated in southern Argentina. The
Corporation presently has 190,158,851 shares issued and outstanding.
This news is submitted by Allen V. Ambrose, President and Director of Minera Andes Inc.
For further information, please contact: Art Johnson at the Spokane
office, or Krister A. Kottmeier, investor relations -- Canada, at the
Vancouver office. Visit our Web site: www.minandes.com.
Spokane Office
111 East Magnesium Road; Ste. A
Spokane, WA 99208 USA
Phone: (509) 921-7322
E-mail: info@minandes.com
Vancouver Office
911-470 Granville Street
Vancouver, B.C. V6C 1V5
Phone: (604) 689-7017; 877-689-7018
E-mail: ircanada@minandes.com
Caution Concerning Forward-Looking Statements:
This news release contains forward-looking statements and
forward-looking information within the meaning of applicable US and
Canadian securities laws. Such forward-looking statements or
information include, but are not limited to, statements or information
with respect to the price of gold, silver, copper and other base
metals, operating and capital costs, production estimates, and
estimation of mineral reserves.
In making the forward-looking statements and providing the
forward-looking information, we have made numerous assumptions. These
assumptions include among other things, assumptions about the price of
gold, silver, copper, anticipated costs and expenditures, future
production and recovery and that there is no unanticipated fluctuation
in interest rates and foreign exchange rates. Although our management
believes that the assumptions made and the expectations represented by
such statements or information are reasonable, there can be no
assurance that the forward-looking statements will prove to be
accurate. Forward-looking statements and information involve known
and unknown risks, uncertainties and other factors that may cause our
actual results, to be materially different from that expressed or
implied by such forward-looking information. Such risks,
uncertainties and other factors include among other things, declines
in the price of gold, silver, copper and other base metals, the
outcome of the Solitario Claim, capital and operating cost increases,
changes in general economic and business conditions, including changes
in interest rates and the demand for base metals, economic and
political instability in Argentina, discrepancies between actual and
estimated production and mineral reserves and resources; operational
and development risk; the speculative nature of mineral exploration
and regulatory risks.
Readers should not place undue reliance on forward-looking statements or
information. We undertake no obligation to reissue or update
forward-looking statements or information as a result of new information
or events after the date hereof except as may be required by law.
See our annual information form for additional information on risks,
uncertainties and other factors relating to the forward-looking
statements and information. All forward-looking statements and
information made in this news release are qualified by this cautionary
statement.
Cautionary Note to U.S. Investors:
The United States Securities and Exchange Commission (the "SEC") permits
mining companies, in their filings with the SEC, to disclose only
those mineral deposits with "mineral reserves" that a company can
economically and legally extract or produce. We use certain terms in
this news release, such as "mineral resources", that the SEC guidelines
strictly prohibit us from including in our filings with the SEC,
because these terms are common usage in Canada and form part of our
Canadian filing requirements. U.S. Investors are urged to consider
closely the disclosure in our Form File No. 40F, which may be secured
from us, or from the SEC's website at
http://www.sec.gov/edgar.shtml.